Timeline date: 2019-2020
Stage: Compensation Phase
Ministry of Energy set aside 5.2 billion TZS in 2019/20 financial year. First phase payments completed by May 2020. TPDC initially withheld payments from 39 PAPs due to verification issues, later resolved by October 2020.
Key players:
- Ministry of Energy
- TPDC
- PAPs
Details:
- Compensation Budget: 5.2 billion TZS (2019/20)
- Payment Issues: 39 PAPs initially affected, later resolved
First Phase Compensation Payments
Dec 31, 2018
· Compensation Phase
Ministry of Energy set aside 5.2 billion TZS in 2019/20 financial year. First phase payments completed by May 2020. TPDC initially withheld payments from 39 PAPs due to verification issues, later resolved by October 2020.